Delta 4000 Manuál s instrukcemi Strana 28

  • Stažení
  • Přidat do mých příruček
  • Tisk
  • Strana
    / 108
  • Tabulka s obsahem
  • ŘEŠENÍ PROBLÉMŮ
  • KNIHY
  • Hodnocené. / 5. Na základě hodnocení zákazníků
Zobrazit stránku 27
M
81331 Rev 01 Nov 2010
20
When making transformer excitation current measurements conduct all tests on
high-voltage windings only. This reduces the required charging current. In load
tap changers, set to fully raised or fully lowered position for routine tests.
F
WARNING
There is always the possibility of voltages being
induced at the terminals of a test specimen because
of proximity to energized high-voltage lines or
equipment. A residual static voltage charge may also
be present at these terminals. Ground each terminal
to be tested with a safety ground stick, then install
safety ground jumpers, before making connections.
Figure 6: Typical Test Setup for AC Insulation Testing of a Three-Phase Two-Winding Power
Transformer
DELTA4000
HIGH VOLTAGE
UNIT
DELTA4000
TEST SET
CONTROL UNIT
Zobrazit stránku 27
1 2 ... 23 24 25 26 27 28 29 30 31 32 33 ... 107 108

Komentáře k této Příručce

Žádné komentáře